Bartlett HS Renovation Update

We are excited for the renovation work that continues on the campus of Bartlett High School. Several new areas have been in use and are serving our students and staff well. Below is an update on the work that is to be completed in the coming weeks and into the summer. As planned, all renovation work is scheduled to be completed by the start of our next school year. Update: 


– Main building hallway (past the cafeteria): complete in early March
– Auditorium: complete in early March
– Building façade work: over the summer
– Building tower connectors: the West to Main building connector and the East to A building by June. The Main to East building connector by the start of new school year
– Track around the new turf football field: surface installation and striping by end of May
– New Gym: by the start of new school year
– Field House: by the start of the new school year

We appreciate the flexibility of our students, families, faculty, and community during this process. Together, we will have a high school we can all be proud of for many years.